Client
Holland Partner Group
Location
Lakewood, CO
Services
Capital Improvement Renovation
Project Size
$900,000

Project Synopsis

Spyder construction was selected to renovate both the clubhouse and fitness center based on previous performance with the ownership group and design team.

Challenges

Resident impact is often determining factor in the decision to renovate and to what magnitude. The Spyder Team worked with the onsite team to develop a schedule that would minimize resident impact. The fitness center renovation was completed prior to the clubhouse to allow residents to enjoy the renovated amenity space while the clubhouse was being completed.

Results

The Bear Creek clubhouse and fitness center renovation completed within the owner’s timeframe, on approved budget, and with no safety issues.